There hasn’t been much progress over the past few weeks, with Christmas and everything else going on. We’ve also been waiting for the building inspector to approve the new underground drainage before going any further.
The good news is that he signed off the drains yesterday, so we can now cover the pipes and backfill the trench. We’ve started adding more pea gravel around the pipework as required.
Once the trench is filled in, we’ll be ready to move on to excavating the foundations.