March 2020
Our extension drawings: putting the plans on paper
The drawings show the house as it was and how we planned to change it, with a new rear extension and a reworked ground floor.
Planning & decisions
Read article →OUR BUILD DIARY
Follow our extension from the garden before we started through demolition, drainage, foundations and building the walls. Read the whole story or explore a stage of the build.
38 progress articles · Entries without exact dates follow the build sequence.
March 2020
The drawings show the house as it was and how we planned to change it, with a new rear extension and a reworked ground floor.
Planning & decisions
Read article →End of summer 2020 · Posted 23 October 2020
This is the back garden as it looked at the end of the summer, before work began. The block paving stretches right up to the back of the house, although you can’t see all of it in the photo.
Preparation & demolition
Read article →Early September 2020 · Posted 23 October 2020
The first stage was to move the shed and demolish the existing brick outbuilding and rear porch. We started in early September, while we were in quarantine after our summer holiday.
Preparation & demolition
Read article →Posted 23 October 2020
Demolishing the existing buildings left us with a huge pile of rubble, bricks and blocks, along with plenty of wood to burn.
Preparation & demolition
Read article →Early October 2020
We’ve made a start on the new foul drainage. One of the two existing inspection chambers sits within the footprint of the extension, and the other is where the new rear wall will go. We’re also adding an ensuite, so the drainage layout needs to accommodate that too.
Drainage & services · Planning & decisions
Read article →Date to confirm
A little more progress on the drainage trenches. I’m managing about an hour in the evenings after work, although the nights are drawing in, so I’m not sure how much longer I’ll be able to keep that up.
Drainage & services
Read article →18 October 2020 · Posted 23 October 2020
Another week on, and we’ve made more progress digging the drainage trenches.
Drainage & services
Read article →Date to confirm
More digging today brings us up to date. I’ve ordered the new inspection chambers, pea gravel and some six-metre lengths of pipe. I’ll try to finish preparing the trenches this weekend.
Drainage & services
Read article →19 November 2020
The rain has been relentless for a few weeks, and the days are getting shorter. Our heavy clay soil turns first into a sticky mess, then a sloppy one. When wet, it’s heavier to shift, clings to the shovel and leaves our boots sticking to the bottom of the trench. Progress is slow.
Drainage & services · Planning & decisions
Read article →Date to confirm
We switched over to the new drainage system last weekend. The new soil pipe and inspection chamber are in place, along with several connections on the branch pipe.
Drainage & services
Read article →Date to confirm
There hasn’t been much progress over the past few weeks, with Christmas and everything else going on. We’ve also been waiting for the building inspector to approve the new underground drainage before going any further.
Drainage & services
Read article →Date to confirm
We’ve backfilled the trenches for the new drains. It took longer than expected because the backfill needed to be free of stones larger than 40mm and lumps of clay larger than 150mm. Our soil was full of both, so there was plenty of sorting to do.
Drainage & services · Foundations · Planning & decisions
Read article →16–17 January 2021
The kids helped us clear the rest of the block paving this weekend, earning 5p for every brick they picked up and put into the wheelbarrow or onto the pile.
Preparation & demolition
Read article →23–24 January 2021
On Saturday, we removed almost all the sand that had been beneath the block paving. We filled a one-tonne bag and could easily have filled another four with the amount there was.
Preparation & demolition · Foundations
Read article →Date to confirm
The groundworkers arrived this morning. We removed a panel from our neighbours’ fence and brought the digger across the gardens without any problems.
Foundations
Read article →Date to confirm
The building inspector came today to inspect the trenches. He only stayed a few minutes, as he was happy with what he saw, and we were cleared to pour the foundations.
Foundations · Floor slab
Read article →30 January · Year to confirm (original entry says 2020)
We added flexible joints to the underground drainage where the pipe passes through the foundation. These short sections, known as rocker pipes, allow for differential movement between the pipework and the foundations.
Drainage & services · Foundations
Read article →4 February 2021
A week after the concrete foundations were poured, we’ve received a 15-tonne delivery of hardcore.
Floor slab
Read article →6 February 2021
Before we could start laying hardcore in the extension’s floor area, we needed to move the main water supply pipe from the back of the house.
Drainage & services · Floor slab
Read article →9 February 2021
We’ve started moving the hardcore into place to prepare the sub-base for the floor slab. First, we laid a membrane intended to help stabilise the ground.
Floor slab · Walls & steels
Read article →23 February 2021
We’ve moved about two-thirds of the hardcore into the floor area. The rest will have to wait until the footings are in place.
Floor slab · Walls & steels
Read article →5 April 2021
It’s been a while since my last update. The past eight weeks have been extremely frustrating, although we’re relieved that we paused when we did.
Planning & decisions · Walls & steels
Read article →17 April 2021
With the nights getting a little warmer, we were able to start the blockwork on Saturday afternoon. It feels great to get going at last.
Walls & steels
Read article →24 April 2021
We’re making progress with the blockwork, leaving gaps for the steel posts that still haven’t arrived.
Walls & steels
Read article →17 May 2021
The steel windposts have finally arrived, so after a two-week break we can get going again. While we were waiting, we built the first part of our new deck at the bottom of the garden.
Walls & steels
Read article →19 May 2021
At last, some new photos showing more progress—the ones people signed up for!
Walls & steels · Floor slab · Planning & decisions
Read article →27 May 2021
All of the windposts are now installed!
Walls & steels · Floor slab · Planning & decisions
Read article →17 June 2021
Since the last update, we’ve been making the most of the nice weather, so the building work has taken a bit of a back seat. Looking back over everything we’ve done, though, it feels like good progress.
Drainage & services · Floor slab · Walls & steels
Read article →1 July 2021
We finished filling the cavity with concrete. In the places that will support the sliding doors, we filled it right to the top.
Floor slab
Read article →2 July 2021
The hardcore was ready to be compacted, so we hired a wacker plate for the week. In a few places, it settled more than we had expected, and we had to add extra hardcore to bring it back up to the right level.
Floor slab
Read article →4 July 2021
We moved the sand into place and compacted it with the wacker plate. It took a while to get it level, as the rain had left the sand wet.
Floor slab
Read article →7 July 2021
With the sand finished, the next step was to lay the damp-proof membrane and the insulation boards.
Floor slab
Read article →8 July 2021
The building inspector came today for his first visit since before the foundations were poured. He didn’t stay long and was very happy with everything we had done.
Floor slab
Read article →9 July 2021
Today was concrete day. When I called earlier in the week to book the delivery, there wasn’t a concrete pump available for another two weeks. There was, however, an early morning delivery slot at 7.30am today.
Floor slab
Read article →15 July 2021
We’ve started on the superstructure—the walls above damp course level. The first job was to fix the wall starter kit, which will tie the extension to the existing house.
Walls & steels
Read article →22 July 2021
The blockwork is going up! It has been too hot to work during the day, so we’ve fitted in a couple of evenings this week and last. I also went hiking at the weekend.
Walls & steels
Read article →7 August 2021
The walls are slowly getting higher, and we’re now close to head height on both sides of the extension. It’s encouraging to see the structure taking shape.
Walls & steels
Read article →Date to confirm
We’ve uncovered some odd things buried in the garden, both during the extension build and while digging for other projects.
Preparation & demolition
Read article →